Pipeline Lowering

senseadmin
1 Min Read
Disclosure: This website may contain affiliate links, which means I may earn a commission if you click on the link and make a purchase. I only recommend products or services that I personally use and believe will add value to my readers. Your support is appreciated!

1.    Lowering shall commence after inspection of trench.

2.    Trench bottom shall be free from pipe supports, stones, roots, debris, stakes, and rigid material.

3.    Padding shall be provided in rocky/ murram area.

4.    Lowering shall commence as soon as possible after completion of joint coating.

5.    Before lowering in, complete check by a full circle holiday detector for pipe coating and field joint coating at 15 KV is carried out (Speed 300mm /sec).

6.    Any damage shall be repaired.

7.    Support/ skid points shall be thoroughly checked.

8.    The pipeline must be laid without interruption for the whole or the length of section available.

9.    Ends of the lowered pipeline section shall be closed with night cap to prevent ingress of water, mud etc.

               

Share This Article
Follow:
Prabhu TL is an author, digital entrepreneur, and creator of high-value educational content across technology, business, and personal development. With years of experience building apps, websites, and digital products used by millions, he focuses on simplifying complex topics into practical, actionable insights. Through his writing, Dilip helps readers make smarter decisions in a fast-changing digital world—without hype or fluff.