Heaters, Deaerators , Plate Type Exchangers , Coolers Etc Part II _ Abc Of Thermal Power Plant
Part I i have discussed about the heaters ,coolers heat exchangers etc. In this blog I will discuss about the…
Part I i have discussed about the heaters ,coolers heat exchangers etc. In this blog I will discuss about the…
Beside that in Turbine package there are other auxiliaries both static and rotary such as different coolers , CEP (…
Earth pit checking Each earth pit is checked as mentioned in the standard check list of Switch yard earthing…
220 volt DC system The 220V DC system supplies direct current as source of operating power for control, signaling, relays,…
COMMISSIONING PROCEDURE: TESTING OF BATTERY CHARGERS: The insulation value shall be checked with 500 V DC Megger. During this…
Till last dispatch basics electrical system discussed which are essential for the erection and commissioning of the Power system. Earthling…
Opening has been kept at service bay side to lift panels as shown in the above picture. Cable spreader…
PRE – ENERGISING CHECKS & TESTS -Inspect any physical damage in the busbar, insulation, panel doors, power & sliding contacts…
Besides HT cubicles other common electrical items are transformer , LTMCC ( Low tension Motor eontrol center ) , Different…
415 Volts LT switch gear consists of two bus sections A&B with a bus coupler between them. The two…
COMMISSIONING Carry out functional checks to prove the operation of interlocks/inter-tripping between the 415 Volts incoming and bus coupler breakers…
Steam blowing of MS lines, CRH,HRH,SH,RH,HP & LP bypass pipe lines of turbine is carried out in order to remove…