Electrical System Of A Thermal Plant Concluding Part- Abc Of Thermal Power Plant
Earth pit checking Each earth pit is checked as mentioned in the standard check list of Switch yard earthing system Check that the depth of the earth pit is…
Electrical System 220 V Dc System For Main Plant- Abc Of Thermal Power Station
220 volt DC system The 220V DC system supplies direct current as source of operating power for control, signaling, relays, tripping and closing of switchgears, emergency motors of most important…
220 Volt Dc System-Battery Charger -Commissioning Part -I I-Abc Of Thermal Power Plant
COMMISSIONING PROCEDURE: TESTING OF BATTERY CHARGERS: The insulation value shall be checked with 500 V DC Megger. During this test, all low voltage circuits & Relays etc, shall be …
Electrical System ( Ht ) Panel 11kv For Equipments And System (Part -I)- Abc Of Thermal Power
Till last dispatch basics electrical system discussed which are essential for the erection and commissioning of the Power system. Earthling rods and flats are laid at different places when civil…
Ht Switchgear Erection ,Testing And Commissioning (Part-II) -Abc Of Thermal Power Plant
Opening has been kept at service bay side to lift panels as shown in the above picture. Cable spreader room erection of cable trays under progress. This is below…
Pre Charging Test And Commissioning Of Ht Switch Gear (Typical) -Abc Of Thermal Power Station
PRE – ENERGISING CHECKS & TESTS -Inspect any physical damage in the busbar, insulation, panel doors, power & sliding contacts etc. and to be rectified if found. Special attention to…
Electrical System (Lt) Installation , Pre-Commissioning , Commissioning Of Different Ltmcc -Abc Of Thermal Power Plant
Besides HT cubicles other common electrical items are transformer , LTMCC ( Low tension Motor eontrol center ) , Different Power distribution board coming under lighting packages etc. In this…
Electrical System (Lt) Installation , Pre-Commissioning , Commissioning Of Different Ltmcc -Abc Of Thermal Power Plant Part -II
415 Volts LT switch gear consists of two bus sections A&B with a bus coupler between them. The two sections are fed from two individual power transformers 1A and…
Electrical System (Lt) Installation , Pre-Commissioning , Commissioning Of Different Ltmcc -Abc Of Thermal Power Plant Part -III
COMMISSIONING Carry out functional checks to prove the operation of interlocks/inter-tripping between the 415 Volts incoming and bus coupler breakers in each switchboard & MCC. Carry out functional checks to…
Steam Blowing Part -/I Abc Of Thermal Power Plant
Steam blowing of MS lines, CRH,HRH,SH,RH,HP & LP bypass pipe lines of turbine is carried out in order to remove welding slag, loose foreign materials, iron pieces, rust etc. from…