Cost Breakup for a Pipeline Project

Sr.No. Item Description Percentage of Capital Cost Liquid Lines Gas Lines 1 Survey, ROW and Compensation 2% 1% 2 Line Pipe Steel Cost 33% 45% 3 Main Line Materials 2% 3% 4 Coating of Pipes 11% 6% 5 Main Line Construction 33% 25% 6 Cathodic Protection 1% 1% 7 Telecommunications, SCADA and RCPs 5% 2% […]

Sr.No.Item DescriptionPercentage of Capital Cost
Liquid LinesGas Lines
1Survey, ROW and Compensation2%1%
2Line Pipe Steel Cost33%45%
3Main Line Materials2%3%
4Coating of Pipes11%6%
5Main Line Construction33%25%
6Cathodic Protection1%1%
7Telecommunications, SCADA and RCPs5%2%
8Pump / Compressor Stations5%12%
9Delivery Terminal Facilities2%1%
10Project Management5%4%
 SubTotal100%100%