Base Case Experiment (single-pass waterfall)

Prabhu TL
1 Min Read
Disclosure: This website may contain affiliate links, which means I may earn a commission if you click on the link and make a purchase. I only recommend products or services that I personally use and believe will add value to my readers. Your support is appreciated!

As a base-case, we start by executing the model in “waterfall mode” by using our ‘Switch for Waterfall”. It yields the following results:

Project End Time: 79 Weeks (see Figure 68). Note that the project end time is the point at which all of the work backlogs have been depleted.

Project Cost: 250,223 tasks (see Figure 69). Note that for management, this is translatable into a dollar cost. We are currently using “task” as a fungible unit of work. This can easily be substituted with person-hours. Using this in conjunction with labor costs, we can quickly determine the dollar amount of the effort spent. For our purposes, however, “task” is an acceptable unit of cost.

Project Quality: 277 tasks (see Figure 70). Note that here we are measuring quality by the amount of undiscovered rework tasks that escape into the delivered product.

In summary, our base case scenario produced the following project performance:

Share This Article
Prabhu TL is a SenseCentral contributor covering digital products, entrepreneurship, and scalable online business systems. He focuses on turning ideas into repeatable processes—validation, positioning, marketing, and execution. His writing is known for simple frameworks, clear checklists, and real-world examples. When he’s not writing, he’s usually building new digital assets and experimenting with growth channels.