| Clause | Details |
| WLD-FAB-001 | Applicable codes for welding are ASME B31.3, ASME Boiler and Pressure Vessel Code. |
| WLD-FAB-002 | In India, additionally IBR Regulations Apply. |
| WLD-FAB-003 | Normally in hydrocarbon insustry, Carbon Steel, Alloy Steel and Stainless Steel are the base materials to be welded. |
| WLD-FAB-004 | Welding consummables include Electrodes, Filler Wires, Argon gas etc. |
| WLD-FAB-005 | Quality of welding consummables must be ensured as per Project Welding Specification. |
| WLD-FAB-006 | Argon gas shall be 99.995 Percent Pure. |
| WLD-FAB-007 | Welders must be qualified as per applicable code e.g. B31.3 |
| WLD-FAB-008 | All the welding equipment like transformers, thermocouples, pyro-meters, automatic temperature recorders, heat treatment equipmets etc. is provided by welding contractor. |
| WLD-FAB-009 | All the weld testing equipment like radiographic equipments, radiographic films, darkroom facilities, dye-penetrant testing, magnetic particle testing, ultrasonic testic etc. are provided by the welding contractor. |
| WLD-FAB-010 | Generally used welding processes are SMAW and GTAW. |
| WLD-FAB-011 | SMAW : Shielded Metal Arc Welding Process |
| WLD-FAB-012 | GTAW : Gas Tungsten Arc Welding Process |
| WLD-FAB-013 | Which welding process to be emplyed where is given in Project Welding Specification. |
| WLD-FAB-014 | Edge preparation procedure required to be carried out for different types of base materials. |
| WLD-FAB-015 | Cleaning of the edge is necessary. |
| WLD-FAB-016 | After cleaning, edges are aligned and properly spaced. Tack welding, if required is done. |
| WLD-FAB-017 | Workpieces need to be protected form weather during welding. |
| WLD-FAB-018 | Proper welding technique is usually specified in Project Welding Specification. |
| WLD-FAB-019 | Welding procedure qualification record should be submitted by Welding Contractor to the Client. |
| WLD-FAB-020 | Preheating and Post Weld Heat Treatment need to be carried out as per Project Weldng Specification. |
| WLD-FAB-021 | After welding and PWHT, Inspection and Testing of welds is done as per various testing and inspection methods specified in Project Welding Specification. |
| WLD-FAB-022 | Repairs of welds may be done if defects are within certain limits. |
| WLD-FAB-023 | Contractor has to submit various documents related to welding work done by him. |
Piping Welding

Prabhu TL is an author, digital entrepreneur, and creator of high-value educational content across technology, business, and personal development. With years of experience building apps, websites, and digital products used by millions, he focuses on simplifying complex topics into practical, actionable insights. Through his writing, Dilip helps readers make smarter decisions in a fast-changing digital world—without hype or fluff.